Monday, February 4, 2019

Diesel fuel distributor open for business

After looking at a few on line photos of tank car unloading I came up with this arrangement for the diesel fuel distributor.
The Chevron diesel fuel distributor in Battle Mountain is now finished and has received it's first shipment of product from the company's refinery in Richmond, California.  I now have an excuse to buy a few more of the right tank cars.

Thursday, January 31, 2019

Scratch built end of track bumpers

I like to have nice end of track bumpers at the ends of my spur tracks.  After seeing some scratch built ones on the Internet done in larger scales I decided to make my own N scale ones from brass.  I used this photo of something done in a larger scale as a reference.
The materials used include scraps of code 55 rail, PCB ties, and brass stock and all soldered together.  This photo shows the one I made for the diesel distributor before I had painted it.






Here is the same bumper after painting, being glued into place, and some ballast and scenery added.  The PCB tie material is covered by the scenery.
Because it is made of brass and can conduct electricity it is important to keep the bumper from actually touching the track.  I somehow blew it on this one at the warehouse and had to cut a gap in one of the rails to clear a short as shown in this photo.

Saturday, January 26, 2019

Progress on the Diesel fuel distributor

There is actually a fuel transfer facility in Battle Mountain and I am including a similar facility on my layout.  The purpose of my facility is to distribute Diesel fuel to the many mining operations in the area that maintain their own fuel pumps for their mining equipment.
I already had a good start on this industry by using parts left over from past layouts and posted about this just about a year ago in the post Reuniting a Walthers Interstate Fuel & Oil kit.  As the site of this facility was near the edge of the Battle Mountain section I decided to wait until the Harney section was installed to finish it.

The Faller silo kit I used on the Diamond Plastics complex had a tool for bending the ladder safety cages that same with that kit.  I found that this tool works just as well in shaping the safety cages from Gold Metal Models.


Here are the storage tanks with the ladders installed.  The concrete base shown here is removable so all the work can be done at the bench then placed back on the layout.

Here is the same scene after a few more details were added to the tanks and they were painted.  The truck loading platform is from the Walthers Interstate Oil kit and the pump is from the old Micro Engineering gas station kit.  Still a bit more to do here and some weathering.




Next I will need to work on how the Diesel fuel is removed from the tank cars, that will be in the next post.

Monday, January 14, 2019

A belated happy new year

We are already half way through January and I have yet to make a post.  We were in Arizona visiting family and got back a couple days ago.  Time for an update.

Before leaving for Arizona I had ballasted both lines where they connected between the Battle Mountain and Harney sections and started to blend the scenery in the area.  After giving the track a good cleaning the main line has now re-opened.
Again this year I am taking part in the Trainboard.com winter layout party.  Besides presenting a few projects on the home layout I am also giving one of my Ntrak modules a tune up with the goal of displaying it in a layout at a show in late February.

Wednesday, December 19, 2018

Creating a place for the DCC system

Up to this point in the layouts life the DCC system has been sitting on the floor under the staging yard.  The command station and power supply are attached to a piece of plywood with a small section of track with the output being being at a jack that the layout can be connected to.  I have often taken this setup with me to Ntrak layout setups to use as a programming station.

What I decided on was a similar setup that is mounted in a drawer that is directly under the bridge on the Harney section.  This is right next to the work bench so a test / programming track can be on the bench where I wanted it.  I actually reused the same drawer hardware salvaged from the last layouts control panel.


There is room underneath to set up a spare computer to use as a JMRI programmer.

So now with the old setup gone and not available to take to shows I think I better get going on building the long promised programming station for the Ntrak club.

Wednesday, December 12, 2018

Home made throttle holders

Several years ago I bought a couple of these throttle holders from a local shop and have really liked them.  These are designed to fit the throttles from several different DCC manufacturers.




The layout as grown to the point that I wanted some more but they don't seem to be in shops any more and on line they are now about $15.00 each which is quite a bit more than what I had paid before so I started looking at making my own using scraps.  It needed to be simple and only had to work with Digitrax throttles.

The design I came up with uses 6 scraps of 1/4 inch plywood and tempered hard board shown here.  These are the pieces and sizes.

1 Hard board back 4.25" x 3.00"
2 Hard board fronts 4.25" x .562"
1 Plywood bottom 3.00" x 1.00"
2 Plywood sides 4.00" x 1.00"



Here is the throttle holder after being assembled with yellow carpenters glue and sanded.   I rounded the top corners on the front strips before assembly.   There are a couple of mounting holes in the back which can't be seen in this photo because of the throttle.

I test fitted several types of Digitrax throttles and they all fit nicely.  I don't know if this would work with throttles of other DCC brands.





I like these home made holders well enough that I may make these standard for the home layout as they will all look the same.  Then adapt the other holders for use on the Ntrak modules.

Friday, November 30, 2018

The latest layout expansion

The Harney section has been installed into the layout and the end of it was close enough to the old test layout to connect to it rather than use the turn around loop again.   Bridges were made from scraps and tracks laid across connecting the layouts.



The test layout is Kato Unitrack on a shelf that has been changed many times in the last 5 years. This latest configuration is a combination of return loop for the main layout while still being an operating layout by itself.  More about that in a future post.



Monday, November 19, 2018

Trying my hand at sky board painting

In preparation for installing the Harney section into the layout the plastic sky board needed to be extended and as only the first few inches above the mountains would show I thought I would paint a sky backdrop to match the sky that is on the photo backdrops.

The test layout that has been along the end wall was taken down for access and another 16 inch wide sheet of fiberglass reinforced plastic panel was installed.  Seams and nail holes were patched with Spackle and then the panel was painted the wall color.
I have been using Artist Acrylic paints for my river bottoms and happy with those results picked up what I thought was a light blue and some white to add to my collection for working on sky boards.
I read somewhere that the higher sky is slightly darker than close to the horizon and that can be seen in the photo backdrops.
Even with lightening the blue, it dries a bit darker so I kept lightening.  Getting closer with each application.  I think when all is right I may need to spray some flat to get rid of the reflections from the lights.
The Winnemucca area also has a small sky board that I am painting.  This one also needs some lightening.

It's fun working with these Acrylic paints to get the results I want.  I may also try adding some clouds as I go along.

Sunday, November 11, 2018

Installing the BLMA bridge

One of the first things I purchased when planning this layout was one of the BLMA brass thru truss bridges.  The time has finally come to install in on the layout.

This bridge comes with nicely detailed bridge shoes so I did not need to add any like I did with the Central Valley bridge I have in another area of the layout.

The vertical girders on the bridge are spaced at 25 foot intervals, the same as the Central Valley bridges so length wise the Central Valley bridge ties fit perfectly.  I did find that with the walkways on the BLMA bridge the ends of the ties would not fit so I trimmed them off as shown in this photo.
After removing the ties on a section of Micro Engineering flex track I applied a coat of Plyobond adhesive to the bottom of the rails and set the rails into the the slots on the Central Valley bridge ties.

 After the adhesive has set overnight, I painted the entire assembly rail tie brown.  Before the paint fully set I removed the paint from the tops of the rails with a razor blade.
The bridge comes with nicely detailed stainless steel walkways.  The decks are left unpainted and the handrails and support structure are painted a semi-gloss oxide red.  I felt these things were too shiny so I removed them and air brushed them a flat oxide red.






Here is one of the walkway assemblies after painting.   These were attached to the bridge with CA so I will re-attach them the same was.


The bridge itself got an overall weathering using acrylic black weathering wash to bring out all the great details in this model.  Then some rust highlights were added with weathering powders. In this photo it is temporarily set in place.
The walkways were glued back into place.  A bit of adhesive was spread along the runners that support the track and the painted section of bridge track was set in place and weighted until the adhesive set.
The bridge shoes were then attached to the bridge abutments with adhesive and the track on the line connected to the smaller section of bridge track.





I am quite happy with the way this came out and seeing the 200 ft camel back version of this bridge still available on ebay I am tempted to get one for another crossing down the line.